ARCWAY Cockpit

Synchronizing Tasks with MS Project™

Data Exchange with MS Project™

Tasks can be

Work items cannot be exchanged with MS Project.

The underlying concept for the first option is as follows:

Synchronize

You can synchronize tasks with MS Project. Synchronization works in two phases. In the first phase the fields Actual Work and Work Forecast are updated in the MS Project file. In the second phase new tasks in the MS Project file are added to ARCWAY Cockpit, tasks that no longer exist in the original file are removed from ARCWAY Cockpit and existing tasks are updated.

Please note that you can only synchronize project plans with MS Project.

To synchronize tasks with MS Project...

  1. Select the desired project in the Project Navigator
  2. Right click the root node of the project and select Synchronize in the context popup menu. This will activate the synchronize wizard
  3. Select Synchronize tasks with Microsoft Project and click Next.
  4. On the next page you may select the project plan and the file to be synchronized.

    Once again, hit Next to get to the next page

  5. On this page you may select which tasks shall be synchronized and which fields (Actual Work and Work Forecast) in the MS Project file shall be updated.

  6. Finally, hit Finish and the selected tasks will be synchronized*

When you synchronize a project plan, the existing project plan in ARCWAY Cockpit is updated to reflect the changes of the project plan being imported. This means...