ARCWAY Cockpit

Edit Dialog for Tasks

Edit Dialog for Tasks

Note: Tasks can only be edited in ARCWAY Cockpit until they have been synchronized with MS Project.

Fields

1 - Name

Name of the task. This is a mandatory field

2 - Start

Start data of the task. This field should be entered when the task is created

3 - Duration

Duration of the task in days

4 - Finish

End date of the task. This field should be entered when the task is created

5 - Work top down

Estimation for the work required to complete the task. This field should be entered when the task is created

6 - Milestone

This task is a milestone. Such a task does not have any duration, work (top down) or work items.